1 Tram · Zürich · 2023 – 2029
Limmat Tram Extension
4.2 km of new tram line, seven stops and a car-free bridge, connecting 38,000 residents to the centre in under fifteen minutes.
4.2 kmnew double track
7new stops
−11 minaverage trip to the centre
+38%jobs within 15 minutes
Where we are
Study2023
Options2024
Designnow
Approval2027
Opening2029
Timetable
| When | Milestone | Who | Status |
|---|---|---|---|
| Q2 2023 | Corridor study & demand model | Knoten, city transport office | Done |
| Q1 2024 | Three route options, public exhibition | Knoten, residents' forum | Done |
| Q4 2024 | Preferred route agreed by council | City council | Done |
| 2025 – 26 | Detailed design, stops and bridge | Knoten + engineers | In progress |
| 2027 | Planning approval | Canton | Scheduled |
| 2029 | Opening day | Everyone | Scheduled |