Harbourfront Tower B

A 32-storey rental tower on Toronto's waterfront, built on a six-day floor cycle with a self-climbing core two levels ahead and 386 bathroom pods craned in finished.

Rising · L27 of 32
Storeys
32
Height
104m
Units
386
Gross floor area
31,400m²
Structure
PT flat slab
Floor cycle
6days
Contract
GMP · C$186M
Top-out
Jan 2027
Harbourfront Tower B in its waterfront context, with climbing screens and a tower crane at the top

The brief

386 homes, open before the lease-up season.

The developer had a fixed date: first residents in by September 2027, or a full year of rent lost. The original programme, built on a conventional crane-led sequence, topped out in June 2027 — far too late to fit out 386 homes.

We re-planned the tower around its core. A hydraulic self-climbing rig takes the core walls up two levels ahead of the slabs, so the crane is free for tables, rebar and pods. Post-tensioned flat slabs cut the reinforcement on every deck by a third and let us strip forms after three days.

What changed

  • Top-out brought forward five months, to January 2027
  • 386 bathroom pods built and water-tested off site
  • Facade installed from the slab edge — no external scaffold
  • Zero lost-time injuries across 640,000 hours

Live progress

Floor by floor.

Updated every morning from the site diary. Each bar is one level; colours follow the trade sequence from structure to handover-ready.

Floor status: levels 1 to 12 complete, 13 to 18 in fit-out, 19 to 24 envelope, 25 to 27 structure with the level 27 slab pour on Thursday, core walls at level 29, levels 30 to 32 not started.

Live · Week 86 of 128

27/ 32 slabs poured · 84%

StageLevelsStatus
CompleteL01–L12Podium, amenity and 9 residential floors handover-ready
Fit-outL13–L18Kitchens, flooring and pod connections
EnvelopeL19–L24Unitised panels from the slab edge, two floors a week
StructureL25–L27L27 slab pour Thursday, 06:00
Core aheadL28–L29Jumpform rig at L29, next climb Saturday
To comeL30–L32Penthouse floors and plant level

Current: L27 slab pour Thu6-day cycle · core +2

The six-day floor cycle

How one floor goes up.

On Tower B the cycle starts on a Friday so every pour lands on a Thursday — clear of the weekend shutdown at the batching plant.

Day 1

Set out & jump core

Surveyors mark grid lines and sleeves; the core rig climbs one level with its screens.

Survey · core crew
Day 2

Strip & fly tables

Table forms are stripped from the level below and flown up by crane, 14 lifts before noon.

Formwork · crane
Day 3

Deck, edges & protection

Infill decking, edge forms and perimeter screens closed before any trade steps on.

Formwork · safety
Day 4

Rebar & PT tendons

Bottom mat, banded and distributed tendons, chairs, then the top mat over the columns.

Rebar · PT crew
Day 5

Cast-ins & inspection

Pod drains, risers and electrical sleeves; engineer's and inspector's pre-pour sign-off.

MEP · engineer
Day 6

Pour

Two pumps, 142 m³ of 40 MPa concrete, placed and power-floated by 13:00. Stress tendons at 72 hours.

Concrete · pump

Drawings

Built on paper first.

Building section through the tower with slabs, columns and core stair

S-201Section through core and typical floors

Typical residential floor plan

A-112Typical floor, L06–L30

Massing model of podium and tower

M-001Podium and tower massing

Programme

From hoarding to handover.

  1. Feb 2025MobiliseHoarding, tower crane, shoring
  2. Apr 2025Core startsJumpform rig assembled at L01
  3. Sep 2025Podium doneTypical cycle begins at L06
  4. Oct 2026L27 pour5 slabs to go
  5. Jan 2027Top-outCrane down by March
  6. Aug 2027HandoverPhased from L01 upward