CS-218 // Architectural // F4

Merri Creek Library

A two-storey public library on the creek flats in Coburg, built almost entirely in exposed concrete. 2,100 m² of board-marked walls, a post-tensioned reading-room roof and not one patch-repair at handover.

ClientCity of Merri
ArchitectHalden Ruiz
ContractD&C subcontract
HandoverApr 2025
Batch docket summary · Merri Creek LibraryNo. CS-218 / 046
Concrete placed
6,840m³ in-situ
Reinforcement
742tonnes fixed
Pours
46incl. 14 wall lifts
Finish class
F4board-marked
Duration
64weeks on site
Lost-time injuries
0186,000 hrs

Pour 03 // Brief

Walls that show every board — and no mistakes.

The architects wanted the building to read as one continuous cast: rough-sawn hoop pine boards, 95–125 mm wide, running unbroken through every lift and around every corner. No visible pour lines, no grout loss at the joints, and tie holes on a strict 600 × 450 grid.

We built three 1.2 × 1.2 m sample panels in the yard before tender, testing two release agents, two board-seasoning methods and a C50/60 self-compacting mix against a conventional vibrated one. The SCC panel won by a mile.

  • Formwork design, shop drawings and pour sequencing in-house
  • Boards pre-seasoned with cement slurry for an even first cast
  • Lift joints hidden in a 20 mm rebate on the board line
  • Every wall face scanned and signed off against the sample panel
North elevation of Merri Creek Library showing the long board-marked concrete facade
Drawing A-201North elevation · 1:200

Pour 04 // Drawings

The drawing set we poured from.

Our temporary-works team issued 212 formwork shop drawings for this job — every board, tie, cone and pour stop set out before a single sheet of ply was cut.

Long section through the library: basement, ground floor, reading room and post-tensioned roof
Drawing S-301Section B–B · 1:100
Ground floor plan with wall layout and pour zones
Drawing S-101Pour zones · GF
Axonometric of the wall lifts and roof pour sequence
Drawing TW-044Pour sequence · axon

Pour 05 // Record

Pour log — selected pours.

Ten of the 46 pours. Each was slump- or flow-tested at the truck and sampled for cubes, crushed at 7 and 28 days by an independent laboratory.

CS-218 pour log · Feb 2024 – Jan 2025Targets: C32/40 → 40 · C40/50 → 50 · C50/60 → 60 MPa
Merri Creek Library pour log with mixes, slump and cube strengths
PourDateElementVol.MixSlump / flow7-day MPa28-day MPaResult
P0114 Feb 2024Raft slab, zone A412 m³C32/40100 mm29.644.8Passed
P0406 Mar 2024Raft slab, zone B388 m³C32/40110 mm30.846.1Passed
P0911 Apr 2024GF core walls, lift 196 m³C40/50120 mm38.456.2Passed
P1420 May 2024Board-marked wall W03, lift 164 m³C50/60 SCC680 mm44.966.3Passed
P1705 Jun 2024L01 PT slab286 m³C40/50110 mm37.255.0Passed
P2218 Jul 2024Board-marked wall W03, lift 258 m³C50/60 SCC700 mm46.167.8Passed
P2622 Aug 2024L02 transfer slab344 m³C40/50100 mm36.554.4Passed
P3103 Oct 2024Reading room columns C1–C822 m³C50/60 SCC650 mm45.765.9Passed
P3819 Nov 2024Reading room PT roof slab298 m³C40/50110 mm38.056.9Passed
P4630 Jan 2025Entry stair & ramp walls41 m³C40/50120 mm36.953.7Passed
7-day cube28-day cubeTarget strength 46 / 46 pours passed · 0 cores taken · 0 rejected loads

Pour 06 // Cubes

Cube strength — every C40/50 pour

7-day and 28-day cube results in MPa against the 50 MPa target. Hover a pour to see its 7-day value.

Average 28-day: 55.7 MPa · +11%
7-day cube28-day cubeTarget 50 MPa

Pour 07 // Programme

64 weeks, footing to handover.

  1. Nov 2023Sample panelsThree 1.2 m panels, SCC mix chosen
  2. Feb 2024Raft slab800 m³ in two pours, zones A + B
  3. Apr 2024Cores & walls14 board-marked lifts, 2 per fortnight
  4. Jun 2024PT slabsL01 + L02, stressed at day 3
  5. Nov 2024Reading room roof298 m³ PT roof, one continuous pour
  6. Apr 2025HandoverZero patch-repairs, sealed and signed

“They poured the walls like they were building furniture. The sample panel and the finished wall are indistinguishable.”

Project architect, Halden Ruiz