Register // 214 jobs since 1994
Projects
Nine recent jobs, each one stripped, tested and signed off. Filter by the work we did — the panel markings show the job number, the concrete we placed and the year we handed over.
CS-218
6,840 m³2025
Merri Creek Library
CS-204
22,600 m³2024
Wharf Lane basement
CS-211
14,200 m³2024
Fitzroy Terraces
CS-197
3,900 m³2023
Westgate overflow culvert
CS-189
1,260 m³2022
Yarra Bend Chapel
CS-201
18,300 m³2023
Brooklyn logistics hub
CS-215
11,900 m³2025
Newstead Wharf apartments
CS-222
5,480 m³2025
Moorooka rail underpass
CS-226
2,950 m³On site
Northcote pool & bathhouse
On site // Now
Three pours this week.
Progress is measured in concrete placed against the tender quantity — updated by the site engineers every Friday afternoon.
Northcote pool & bathhouse
Board-marked pool hall walls, lifts 2–4. Balance tank roof pour scheduled Monday 06:30, 186 m³.
1,830 / 2,950 m³ placed · 62%Fitzroy Terraces stage 2
L07 PT slab poured and stressed at day 3. L08 deck in formwork, rebar inspection Thursday.
6,160 / 8,700 m³ placed · 71%Geebung water reservoir
Base slab complete in two night pours. Wall jump-forms erected for the first 3.6 m lift.
1,010 / 4,200 m³ placed · 24%